Neighborhood Action Plan Summary - Phase II
JUMP TO PHASE I REPORT --- JUMP TO PHASE III REPORT
Cedar-Isles-Dean |
Strategy | Plan Funds | Plan Total | Additional NRP Funds | NRP Total | - |
Citation | Strategy Name | Early Access | Action Plan | Phase I Rollover | Reserve Funds | Program Income | Plan Funds for Housing | Mod #s Affecting Strategy |
|
HOUSING |
1.1.1.1. |
Affordable Housing in Minneapolis |
| $153,236.00
| $153,236.00
|
|
| $119,427.01
| $272,663.01
| $153,236.00
| 2,3,4,5 |
1.1.2.1. |
Energy Workshops/Audits |
| $1,872.60
| $1,872.60
|
|
|
| $1,872.60
| $1,872.60
| 1,4 |
1.1.3.1. |
Home Insulation Fund |
|
|
|
|
|
|
|
| |
1.1.4.1. |
Mitigate Adverse Impacts of Southwest LRT |
|
|
|
|
|
|
|
| |
|
COMMUNITY BUILDING |
2.1.1.1. |
Neighborhood Communications |
| $2,000.00
| $2,000.00
|
|
|
| $2,000.00
| $1,420.00
| |
2.1.1.2. |
Newspaper Ads |
| $2,250.00
| $2,250.00
|
|
|
| $2,250.00
| $1,597.50
| |
2.1.1.3. |
Postcard Mailings |
| $3,600.00
| $3,600.00
|
|
|
| $3,600.00
| $2,556.00
| |
2.1.2.1. |
Annual CIDNA Gathering |
| $750.00
| $750.00
|
|
|
| $750.00
| $532.50
| 4 |
2.1.2.2. |
Neighborhood Events |
|
|
|
|
|
|
|
| |
|
NEIGHBORHOOD SAFETY |
3.1.1.1. |
Pedestrian Safety |
|
|
|
|
|
|
|
| 2,4 |
3.1.2.1. |
Sidewalks |
|
|
|
|
|
|
|
| 1 |
3.1.3.1. |
Crime and Safety Initiatives |
|
|
|
|
|
|
|
| |
|
ENVIRONMENT |
4.1.1.1. |
Trees |
| $10,000.00
| $10,000.00
|
|
|
| $10,000.00
|
| |
4.1.2.1. |
Buckthorn Removal |
| $2,500.00
| $2,500.00
|
|
|
| $2,500.00
|
| |
4.1.3.1. |
Cedar Lake South Beach |
| $51,816.47
| $51,816.47
| $42,879.70
|
|
| $94,696.17
|
| 1,2,3 |
4.1.4.1. |
Mitigate Environmental Impacts of Southwest LRT |
|
|
|
|
|
|
|
| |
|
IMPLEMENTATION PLAN |
5.1.1.1. |
Administrative Support |
| $33,394.93
| $33,394.93
|
|
| $25,000.00
| $58,394.93
| $23,710.40
| 4,5 |
|
TOTAL |
| $261,420.00
| $261,420.00
| $42,879.70
|
| $144,427.01
| $448,726.71
| $184,925.00
| |
|
|
PLAN MODIFICATIONS |
No. | Plan Step Modified | Approved | Description |
1 | Full Action Plan | 12/01/14 | The NCR Director approved a plan modification to reallocate $21,127 to Cedar Lake South Beach (Environment 1.3.1.) from the following strategies: (1) $6,127 from Energy Workshops/Audits (Housing 1.2.1.); and (2) $15,000 from Sidewalks (Neighborhood Safety 1.2.1.). |
2 | Full Action Plan | 12/12/16 | The NCR Director approved a modification to the plan to reallocate $42,879.70 of Phase I funds to Phase II strategy, Cedar Lake South Beach (Environment 1.3.1.). (This is Phase I Plan Modification #21 and Phase II Plan Modification #2.) The modification also reallocates a total of $18,462.70 to Cedar Lake South Beach (Environment 1.3.1.) from the following strategies: (1) $17,802.70 from Affordable Housing in Minneapolis (Housing 1.1.1.); and (2) $660 from Pedestrian
Safety (Neighborhood Safety 1.1.1.).
|
3 | Full Action Plan | 09/15/17 | The NCR Director approved a modification to the plan to reallocate $2,156.77 to Cedar Lake South Beach (Environment 1.3.1.) from Affordable Housing in Minneapolis (Housing 1.1.1.).
|
4 | Full Action Plan | 12/30/19 | The NCR Director approved a modification to the plan to reallocate $7,394.93 to Administrative Support (Implementation Plan 1.1.1.). The funds are reallocated from the following strategies: (1) $1,804.53 from Affordable Housing in Minneapolis (Housing 1.1.1.); (2) $0.40 from Energy Workshops/ Audits (Housing 1.2.1.); (3) $5,250 from Annual CIDNA Gathering (Community Building 1.2.1.); and (4) $340 from Pedestrian Safety (Neighborhood Safety 1.1.1.). |
5 | Full Action Plan | 10/25/23 | The NCR Director approved a modification to the plan to reallocate $25,000 in Program Income to Administrative Support (Implementation Plan 1.1.1.) from Affordable Housing in Minneapolis (Housing 1.1.1.).
|
|